Demolition of a building can cause problems for residents and businesses in the immediate area. It is, therefore, important that 6 weeks' notice is given prior to demolition starting and that all disruption is kept to a minimum.
Building control
Phonelines are open between 9am and 12.30pm Monday to Friday, excluding bank holidays.
Address: Coventry City CouncilPO Box 7097
Coventry
CV6 9SL
Demolition notification
It is an offence to start demolition works without giving the right notice. Conditions may need to be imposed, which can only be determined by our visit to the site prior to works starting.
In order to demolish a site in Coventry, you must return the demolition notice form [https://www.coventry.gov.uk/downloads/file/4663/demolition-notice-application-form], giving us 6 weeks' notice. This must show:
- the building and details of the demolition works
- the person undertaking the work
- that the occupiers of adjacent buildings have been informed
- compliance with the Party Wall Act [https://www.gov.uk/party-walls-building-works] has been achieved
- that the gas, electricity and water supplies to the building have been terminated
- drainage to the site has been sealed
- how the site will be secured following completion
When we have received the notice, our Building Control surveyors will visit the site. We will also consult with Highways [https://www.coventry.gov.uk/roads-highways-pavements]. The West Midlands Fire Service [https://www.wmfs.net/] and the Health and Safety Executive [http://www.hse.gov.uk/] may also be consulted.
Once approval for demolition is received, we will require:
- adequate shoring, repair and weather proofing of adjacent buildings
- the removal of material or rubbish
A copy of the demolition notice must also be sent to the utility companies for the building.
It is also a requirement that letters are sent to neighbours of the site providing details of the works and contact information.
Building control
Phonelines are open between 9am and 12.30pm Monday to Friday, excluding bank holidays.
Address: Coventry City CouncilPO Box 7097
Coventry
CV6 9SL
Demolishing the building
When starting the demolition, you must ensure that:
- dust, noise and other disruptions are kept to a minimum
- pavements are not damaged or obstructed
- obstacles and holes are not left where they pose a risk
- all complaints are handled promptly
It is also essential that materials are burned in a controlled manner. Any bonfires [https://www.coventry.gov.uk/pollution-1/bonfires] producing dark smoke are illegal and offenders will be prosecuted.
Building control
Phonelines are open between 9am and 12.30pm Monday to Friday, excluding bank holidays.
Address: Coventry City CouncilPO Box 7097
Coventry
CV6 9SL
Dangerous buildings
If you consider that a building may be dangerous it is important to report it to Building Control by telephone immediately.
Any structure which poses a public risk can be considered dangerous, which includes but is not limited to:
- an entire building
- a building with loose slates or tiles
- garden walls and fences
- advertising hoardings
Depending on the severity of the risk, we will work with emergency services and any other appropriate authorities to deal with the risk.
Building control
Phonelines are open between 9am and 12.30pm Monday to Friday, excluding bank holidays.
Address: Coventry City CouncilPO Box 7097
Coventry
CV6 9SL