Welcome to the Earlsdon Liveable Neighbourhood project page.  Here you can see the latest information on the construction of the scheme. We update this webpage regularly about the work happening now and the next phase of work.

Find out more about the final proposals and the consultation that took place [http://www.coventry.gov.uk/roads-highways-pavements/earlsdon-liveable-neighbourhood-1/2].

16 October update

The Traffic Regulation Orders have now been approved for the 20mph zoned areas, including all signage. These are required before the speed limit changes go live.

14 October update

Bollards to be installed in Arden Street and a resident key holder will be designated including a key to be held by the City Council regarding events. The bollards stop traffic speeding through the street, which in theory will mean the street will be a cul-de-sac. Permanent advance warning signs will be installed ahead of bollards going in. 

This means the following roads will be permanently closed:

  • Arden Street directly outside number 75 at the junction of Clarendon Street.
  • The Shaftesbury Avenue to Beechwood Avenue junction.

1 October update

Following the build-out work and bollards work to slow traffic on Beechwood Avenue to slow traffic hatched markings will be added to the parking area on Beechwood.

Traffic signals will be on Albany Road week commencing 7 October for crossing works. Tactiles will also be installed either of the toucan crossing.

The newly installed Sustainable Urban Drainage (SUDs) on Hartington Crescent will be planted up with plants that will be hardy and attractive all year round. This will assist with slowing rainwater run-off by directing it into an enriched soil bed, and some will slowly drain into the main drainage system to help slow the flow into our rivers. 

Late September and early October update

20mph zone signage and road marking have begun being installed across the liveable neighbourhood. There will be approximately 200 of these in about 40 locations.

27 September update

Lining work on Earlsdon Avenue South has been redone where the pavement on the street from outside number 73 to outside Elsie Jones House near the City Arms pub.

20 September update

Rochester Road is complete apart from the bollards that are on order to be installed shortly. Stoneleigh Avenue works have also been completed this week.

6 September update

Work will be done to build out the curb in the road with bollards and 'Give Way' priority to transfer from Rochester Road to Beechwood Avenue to slow traffic. Four-way lights will be in place by the bus shelter and outside the nursery. Work will last approximately three weeks.

2 September update

Work to install the toucan crossing on Albany Road and the extension of the existing cycleway will recommence after being temporarily paused due to underground utilities needing follow-up investigations. Four-way traffic lights will be in place and the work is expected to take three weeks from 30 Sept meaning the road will have barriers with a gap for pedestrians. The toucan crossing works are due to take place in early October.

Spencer Park entrance back open and build out for toucan crossing commenced with three-way lights. Work in both locations will run consecutively.

Work outside Earlsdon Library, the primary school, and City Arms pub will be completed by the end of this week.  The central reservation has been widened and the SuDs area is now complete and ready for planting.

A new bus shelter has now been installed on Earlsdon High Street, along with new belisha beacons - an orange ball containing a flashing light, mounted on a striped post on the pavement at each end of the zebra crossing – have also been installed and in working order.

12 August update

Work will begin on Earlsdon Avenue South for a two-week period. There will be work to widen the pavement on the street from outside number 73 to outside Elsie Jones House. These improvements will also allow easier access to buses, in the meantime there will be a temporary bus stop. Two way traffic lights will be in place.

29 July update

Work to widen the pavement on Earlsdon Avenue North from Earsdon Primary School down to the island to make the area safer for pedestrians and school children. A Sustainable Urban Drainage (SuDs) will also be installed with bollards. The pavement being resurfaced from the tactile paving outside the library around Albany Road. This work will be carried out within the six-week school holidays to cause minimal disruption. No traffic signals are being used. The central pedestrian crossing area will be fenced off and pedestrians will be guided away from this crossing using signage around the island

15 July update

Work to widen the pavement on the corner of Moor Street onto Earlsdon Street will begin to accommodate room for bike racks. This means there will be a four-week closure on one side down towards the island and a diversion route will be in place. This will take traffic down Earlsdon Avenue South, along Kenilworth Road, and back up Beechwood Avenue. The purpose of this work is to increase space on the pavement for pedestrians and improve visibility. A new zebra crossing will also be installed towards the island.  Access for businesses and affected frontages will remain.

The works will also include resurfacing work outside the City Arms pub up to the bus shelter. A new bus stop has been ordered and will be in place as soon as it becomes available. Slabs have been replaced with a tarmac finish due to the pavement degrading.

11 July update

There will be a permanent closure in place ahead of work starting on Stoneleigh Avenue where it meets with Kenilworth Road. Advance warning signs to be in place from 4 July 2024. Temporary diversion signs will be in place until the works are complete when they will be removed on 19 July 2024. Lit 'No Entry' signs will also be installed.

26 June update 

There will be a full one-day closure with diversions in place on Belvedere Road at the junction of Broadway to install a raised table to slow traffic and improve the pedestrian crossing route into the park.

24 June update 

Work to install the toucan crossing on Albany Road and the extension of the existing cycleway has been temporarily paused due to a high-voltage cable needing further work. In the meantime, improvement works will begin on narrowing the road on the Hartington Crescent/Beechwood Avenue mini roundabout to reduce the speed of cars. Sustainable Urban Drainage (SUDs) will also be installed. Work is expected to last three weeks and three-way traffic lights will be in place. Crews will be offsite after 12 July and planting will take place in September.

28 May update 

Construction has now started.

Beechwood Avenue will be closed for three weeks from 4 June, between Bates Road and Styvechale Avenue. This is to enable us to construct the traffic calming at the Tennis Club entrance, improve the guardrailing at the bend between the Tennis Club and the Golf Club, and to construct the new pedestrian island at the Golf Club. Diversions will be in place, and access for residents and affected frontages will remain.

Please note that sometimes a permit might be requested for longer than the work will take to allow for unforeseen weather and ground conditions.

See below for previous construction updates.

May 2024 update

Construction starting soon

We have finished the statutory consultation on the Earlsdon Liveable Neighbourhood scheme, the third round of public engagement on the project since we first went out to the local community in December 2022.  This means we are now ready to start work to implement the improvements.

Find out more about the final proposals and the consultation that took place [http://www.coventry.gov.uk/roads-highways-pavements/earlsdon-liveable-neighbourhood-1/2].

We will be starting construction on Tuesday 28 May and you may have already seen some activity while we have been getting ready to start.

The work will be phased so that we can minimise disruption.  Work around the schools will take place during holidays, and where possible we will avoid working during major events. This includes Motofest on 1 and 2 June when we will make sure any traffic management for Earlsdon Liveable Neighbourhood is removed during the festival.

Phase one of the work will include:

  • Toucan crossing on Albany Road and extension of the existing cycleway - a Toucan crossing under the railway bridge on Albany Road opposite Spencer Park. This work is expected to take approximately two months and will need some two-way and four-way traffic lights at times
  • Traffic calming features on Beechwood Avenue at the tennis club, improvements to the guard railing at the bend between the tennis club and golf club, and a new pedestrian island at the golf club
  • Raised table at the junction of Broadway and Belvedere Road to slow traffic and improve the pedestrian crossing route into the park.

If you have any questions about the works, please email the project team [mailto:transportprojects@coventry.gov.uk] or phone 024 7697 6544.

Further updates on phasing will be provided on this page.


Sign up for our newsletter for further information about the Earlsdon Liveable Neighbourhood [http://www.coventry.gov.uk/lnemailalerts].

Scheme information

The Earlsdon Liveable Neighbourhood scheme aims to make Earlsdon greener and improve conditions for pedestrians and cyclists.  The scheme design has responded to priorities identified by the local community. 

Scheme proposals to be implemented

Following the three rounds of community engagement and consultation, the main features being introduced are:

  • 20mph zone throughout the scheme - the area bounded by the railway line, Hearsall Golf Club and Kenilworth Road
  • New zebra crossing on Earlsdon Street - between Co-Op and the City Arms
  • New toucan crossing on Albany Road at the entrance to Spencer Park
  • Traffic calming on Beechwood Avenue - including 
    • Changing the layout of the Beechwood Avenue / Rochester Road junction - the road is narrowed and Rochester Road becomes the priority road
    • Narrowing the road at the Beechwood Avenue / Hartington Crescent mini-roundabout
  • Point closure on Arden Street - between Clarendon Street and Hartington Crescent
  • Point closure on Shaftesbury Road - between Beechwood Avenue and St Andrew's Road
  • Pavement widening outside Earlsdon Primary School and Earlsdon Carnegie Community Library - including shortening the distance that pedestrians must walk to cross Earlsdon Avenue North by reducing the road to a single lane towards the roundabout
  • Pavement widening on Earlsdon Avenue South outside Elsie Jones House at the bus stop
  • Benches and planting on Earlsdon Street and Earlsdon Avenue North as part of the zebra crossing improvements
  • Planting on Beechwood Avenue as part of works to narrow the road at the Hartington Crescent mini-roundabout
  • Cycle hire docks on Warwick Street and Earlsdon Avenue - subject to operator approval
  • Cycle contraflow (sign only) Providence Street, Berkeley Road South and Moor Street - no changes to parking or road layout

To introduce these changes, some parking will be relocated, however we have mitigated this by reducing parking restrictions on Albany Road.  These changes collectively support the area-wide 20mph Zone, which would not be effective with signs alone.

View the final proposals here. [https://www.coventry.gov.uk/roads-highways-pavements/earlsdon-liveable-neighbourhood-1/3]

Scheme proposals withdrawn after statutory consultation

Following the Spring 2024 statutory consultation [https://www.coventry.gov.uk/downloads/download/7731/earlsdon-liveable-neighbourhood-traffic-regulation-orders-and-notices-of-intent] and a subsequent cost review process, the following measures will not be implemented:

  • No entry into Warwick Street from Arden Street
  • Changes to parking in Clarendon Street, Warwick Street and Moor Street (between Warwick Street and Clarendon Street)
  • Raised table and road layout changes at the junction of Spencer Road and Dalton Road
  • Raised table at the junction of Beechwood Avenue and Stoneleigh Avenue
  • Taxi rank on Earlsdon Street between Providence Street and Moor Street

More information

In the meantime if you have any questions, please email the project team [mailto:transportprojects@coventry.gov.uk] or phone 024 7697 6544.


Sign up for our newsletter for further information about the Earlsdon Liveable Neighbourhood at www.coventry.gov.uk/lnemailalerts [http://www.coventry.gov.uk/lnemailalerts]

Scheme drawings

Click on each image to enlarge, or you can download a full set of the drawings [https://www.coventry.gov.uk/downloads/download/7851/printable-maps-and-diagrams-for-earlsdon-liveable-neighbourhood] as a PDF.

Albany Road parking changes

Map of Albany Road parking

Albany Road toucan crossing

Map of Albany Road toucan

Arden Street point closure

Arden Street area

Avondale Road no through road sign

Map of Avondale Road no through road

Beechwood Avenue traffic calming scheme - area around the allotments

Map of Beechwood Avenue allotments area

Beechwood Avenue traffic calming scheme - Hartington Crescent mini-roundabout and Arden Street point closure

Arden Street area

Beechwood Avenue traffic calming scheme - Kenilworth Road area

Map of Beechwood Avenue Kenilworth Road area

Beechwood Avenue traffic calming scheme - St Barbara's Church area

Map of St Barbara's Church area

Beechwood Avenue traffic calming scheme - Tennis club area

Map of Beechwood Avenue Tennis Club area

Beechwood Avenue traffic calming scheme - Woodland Avenue area

Map of Beechwood Avenue Woodland Avenue area

Beechwood Avenue traffic calming scheme - Golf club area

Map of Beechwood Avenue golf club area

Berkeley Road South cycle contraflow

Map of Berkeley Avenue South contraflow

Earlsdon Library area

Map of Earlsdon Library area

Earlsdon Street (west) - existing zebra crossing

Map of Earlsdon Street west

Earlsdon Street (east) - new zebra crossing

Earlsdon Street east

Shaftesbury Road point closure

Map of Shaftesbury Road area

Stoneleigh Avenue point no entry

Map of Stoneleigh Avenue point no entry