10. Finance and resources
Part 3 - How will we get there?
10.1 Park Action Plan 2023-2028
This section provides more detail for the tasks that are programmed to take place in coming years.
This section will need reviewing on an annual basis, to enable the management team to bid for finance to carry out the tasks in the forthcoming year.
An action plan for the formal gardens and example action plans can be found in Appendix 5.
Aim |
Objective |
Action |
Responsible officer |
Finance |
Date |
Complete |
---|---|---|---|---|---|---|
MA1 MA2 MA3 MA5 |
MO1 |
Keep signage on site current |
EC |
Core budget |
Annual review/ in line with changes |
Rebrand completed in 2021. Signage will be reviewed and updated regularly in line with identified changes or enhancements. |
MA3 MA4 MA5 MA6 |
MO3 |
Meet with Natural England Attend |
EC, MThack, WM |
Nil cost |
Annually |
Been in contact with NE re HLS payments. Staff also meet with Forestry Commission to discuss felling licence. |
MA3 MA4 MA5 MA6 |
MO3 |
Attend Park Forum meetings and APSE |
EC, MThack |
Nil cost |
Annually |
Midlands Park Forum annual and APSE training for Parks Management |
MA3 MA4 MA5 MA6 |
MO3 |
Work to agreed HLS Agreement |
All Estate Staff and EC |
Grant funded |
Annually (see Estate Action Plan) |
Claim submitted annually - remittance received in November each year. HLS extension agreed to 2028. Reduced grazing regime - Summer 2023. |
MA1 MA2 MA3 MA4 MA5 MA6 |
MO1 MO3 MO4 |
Work to restoration Action Plan |
All Estate Staff and EC |
Core Budget |
Annually (see Estate Action Plan) |
See individual Area Action Plans for dates |
MA1 MA2 MA3 MA4 |
MO2 |
Carry out regular user surveys |
All operational staff |
Officer time |
24 per month April-Sept 12 per month Oct-March |
Visitors per car survey conducted annually. Updated visitor survey produced in 2023. |
MA1 MA2 MA3 MA4 |
MO3 |
Collate and analyse user survey data/ benchmark |
EC |
Officer time |
Quarterly |
Data discussed at team meetings and at Park Project Board meetings (monthly). Benchmarking with Leicestershire parks October 2021. |
MA1 MA2 MA3 MA4 | MO1 MO2 | Meet with key stakeholders | RE & wider Visitor Experience Team |
Officer time | Quarterly/ Project-based | On-site and on-line promotion through face-to-face meetings and awareness. Partnership working with Coombe Abbey Hotel/No Ordinary Hospitality Management. |
MA1 MA6 | MO2 | Continue and Extend Biodiversity Data | MThack, Estate Staff | Officer time/ Volunteers | Ongoing | Butterflies (Butterfly Conservation), hedgehogs, grassland, bat, and reptile surveys by on-site staff or by volunteers. |
MA1 MA6 | MO2 | Continue and Extend Biodiversity Data | MThack, Estate Staff | Officer time/ Volunteers | Monthly WEBS Surveys | Site staff conduct surveys to include annual Heron census, breeding bird surveys. |
MA1 MA2 MA3 MA4 MA5 MA6 | MO1 MO2 MO3 MO4 | Continue review and develop Commerciali- sation Strategy | EC, GMcK, Finance | Officer time | Quarterly |
Go Ape continues to thrive at Coombe Abbey Park, with additional activities mini landrovers progressing. Outdoor Cinema events in May, August and October 2023. The Abbey Artisan Market and Sundae Club dessert diner opened in December 2021 located within the Visitor Centre. Annual Illuminated trail “Luminate Coombe” November to January to 2026. Play area redevelopment - new visitor centre play area opened in June 2022, followed by Hermit’s Hollow pay/play facility opened in July 2023. |
MA2 MA3 MA4 | MO2, MO4 | Continue Staff Training and development | EC, MThack | Officer Time, Core Budget | Health and Safety/ Mandatory Training as required (see Divisional Training Matrix) |
Recruitment training x2 new and refresher x2 Mandatory Training refresher; whole team 2021. Chainsaw refresher training 2021. Chipper training 2021 Water rescue training 2021. |
MA2 MA3 MA4 | MO2, MO4 | Continue Staff Training and development | EC, MThack | Officer Time, Core Budget | Staff Induction |
X3 Inductions of agency staff due to resignations. Interviews for fixed-term contracts – Estate Assistant role 2023. |
MA2 MA3 MA4 | MO2, MO4 | Continue Staff Training and development | EC, MThack | Officer Time, Core Budget | Staff Appraisals | Completed |
MA2 MA3 MA4 | MO2, MO4 | Continue Staff Training and development | EC, MThack | Officer Time, Core Budget | Team Meetings | Monthly as recorded |
MA2 MA3 MA4 | MO2, MO4 | Continue Staff Training and development | EC, MThack | Officer Time, Core Budget | Staff 1 to 1s | Monthly as recorded |
MA2 MA3 MA4 | MO2, MO4 | Continue Staff Training and development | EC, MThack | Officer Time, Core Budget | Attend Midlands Park Forum | Quarterly (with wider Park Service) |
MA3 MA4 | MO4 | Reduce ‘first use’ only resources used to run Coombe Abbey Park | EC, MThack, all staff |
Core Budget | Adhere to CCC carbon reduction strategy ongoing |
On site catering provision continue to use sustainable (plastic free) take away cutlery and packing. Reduction in use of paper – electronic filing system and file sharing. Electric gator fleet progressing through negotiations. |
MA3 MA4 | MO4 | Reduce use of chemical solutions to issues | EC, MThack, all staff | Core Budget | Adhere to CCC carbon reduction strategy ongoing | Hand pulled Ragwort as part of DLL Addition of ‘Paradise’ solution to reduce the amount of chemical treatment required. |
MA3 MA4 | MO4 | Reduce amount of general waste and educate visitors and staff that recycling is an everyday normal activity. | All staff | Officer time Core budget | November 2020 and ongoing |
Recycling unit installed near the visitor centre adjacent to Café in the Park to promote recycling in November 2020. Recycling units for offices. Paper already recycled and collected by Rugby Borough Council. These measures have reduced the spend on the waste budget significantly some of which is down to banning BBQs and recycling practices. Recycling has been reviewed with commercial waste and a more cost-effective solution to its disposal was agreed upon. Public recycling bins require improved interpretation. Glass recycling has been quite unsuccessful. |
MA2 | MO3 | Be aware of current best practice |
EC/MThack/WM | Reservoir S10 and new flood study for state directive compliance 2021/2022 and ongoing. | ||
MA5 | MO2 |
Undertake meetings with Historic England Work with Arboriculture team |
EC/MThack |
Constructive meeting with HE regards the restoration of terrace walls and parterre footpath 2021 and ongoing. Regular communication with Urban Forestry Officer for garden plan development, hazardous trees, dam wall monitoring and introduction of new play facilities 2022/2023. |
||
MA6 | MO2 | Investigate Cormorant control | Estate Team | Ongoing | Cormorant numbers monitored through the winter and a laser is used as a bird scarer. | |
MA7 | MO3 | Liaise with Warwickshire Wildlife Trust | EC/MThack | Ongoing | DLL - Network for Nature projects on Heronry island and siltation study. |
Aim |
Objective |
Action |
Responsible officer |
Finance |
Date |
Complete |
MA1 MA2 |
MO1 |
Rebrand and review and update maps, plans & leaflets, website |
EC MThack & Comms |
Comms routine budget |
Summer 2018 |
Signage update first phase completed; second phase completed April 2021. |
MO3 MO4 MA5 |
MO3, MO4 |
Dunsmore Living Landscape (DLL) Quarterly Project Board Meetings |
EC, MThack |
DLL |
2016 |
2021 and ongoing. |
|
MO3 MO4 |
DLL Acid Grassland restoration |
MThack, EC, WM & PH |
Dunsmore Living Landscape |
2016 |
2019, 2020, 2021 |
|
MO3 |
Meet with Natural England |
EC, M Thack, GMcK |
Nil cost |
Ongoing discussions regarding plan of events at Coombe Abbey Park. |
Ongoing discussions around potential for events to ensure communication between partners. |
|
MO1 MO2 |
Form Friends of Coombe Abbey Park |
RE & EC and wider Visitor Experience Team |
Officer time |
Summer 2018 |
Ongoing although proving difficult. Impacted by Covid-19. |
|
MO1 MO2 |
Incorporate Friends of Comments/Feedback in Management Plan |
RE, EC |
Core budgets |
Autumn 2018 |
See above |
MA1 MA2 MA3 MA4 MA5 MA6 |
MO1 MO2 MO3 MO4 |
Form Commercialisation Strategy |
EC, GMcK, |
Officer time |
Autumn 2018 |
Benchmarking visits or online discussions with CCC Commercial Director ongoing. |
|
MO1 MO2 MO3 MO4 MO5 |
Set up Go Ape business venture at Coombe |
EC, GMcK |
Officer time, Go Ape staff, Finance officers, Natural England & Historic England |
Ongoing |
Project complete April 2019, however additional activities added such as axe throwing 2020. More activity suggestions being discussed although these have been impacted by Covid-19. Additional activities include mini 4 x 4 adventure for children launch anticipated 2022. |